PODS Distribution Facility

Location: Bristol, CT

Project Description

Utilizing the design-build “Team Approach”, ACGNA successfully completed the project within an 8-month time frame – on-time and under budget. ACGNA was chosen by Uniprop, the owner, from a select group of competitors.

In mid-April, ACGNA cleared the site of 13 acres of trees. 22,000 cubic yards of structural fill was imported to elevate the site to the owner’s needs. The 128,000SF facility was con­structed in 180 days. The Certificate of Occupancy was issued December 15th. In addition to the expansive warehouse, an office core with second story meeting space was built-out per the tenant’s requirements.